outage_updates.title

16h52

Outage solved

he power outage is solved
15h55

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 18h00.
14h25

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 16h00.
13h57

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 15h00.
12h51

Repair time extended

Unfortunately we need more time to solve the outage. Probable new end time is 14h00.
11h44

Power outage identified

Outage discovered by Sibelga at 11h43
Probable end time: 13h13.